Project Description

Sipsmith Gin Distillery were experiencing some extreme high temperature throw off heat from their existing 2No. Distillery Chiller Systems and of which were not only causing an uncomfortable working environment for their staff, it was also starting to cause operational issues with their existing IT/Comms Systems.

UM&E were asked to help resolve this issue with the design and installation of a brand new Chiller Extract System consisting of:

  • 3No. Separate Ductwork Systems
  • 3No. Inverter Driven Air Extract Fans
  • New 3 Compartment Air Extract Plenum Chamber
  • External Air Intake & Extract Wall Louvre’s
  • Control Panel with inbuilt PRIVA Touch Screen Control to manage, monitor and run the complete system.

Completion of works just in time for the start of the warm weather and with an extremely happy client feeling a lot cooler!

 

Works Completed

  • Mechanical Extract System Design
  • Design & Install Electrical Services
  • Design & Install BMS Controls
  • Design, Manufacture, Supply & Install Extract Fan Control Panel
  • Supply & Install Mechanical Ductwork System
  • Supply & Install Inverter Driven Extract Fans
  • Supply & Construct 3 Compartment Air Extract Plenum Chamber
  • Supply & Install External Air Intake & Extract Louvre’s
  • Relocation of existing Incoming Main Water Supply
  • General Builders works including the removal of an existing redundant roof mounted boiler flue and associated roof repair works.